DPWH to start C5 road rehabilitation later this month

Nov 4, 2026

3:37 PM GMT+8

DPWH to start C5 road rehabilitation later this month

ROAD REHABILITATION. Department of Public Works and Highways Secretary Giovanii Lopez (center) and Department of Transportation Secretary Vince Dizon (right) during the inspection of the newly reopened Pasig Boulevard-C5 Flyover in Bagong Ilog, Pasig City on Tuesday (Nov. 3, 2026). Lopez said they are looking to start the C5 rehabilitation project later this month. (Screengrab from DPWH video)

MANILA – The Department of Public Works and Highways (DPWH) is looking to start the C5 rehabilitation project later this month, DPWH Secretary Giovanni Lopez said Tuesday.

 

“Based on our meetings with the DPWH-NCR (National Capital Region), the rehabilitation of C5 – which we have previously discussed – is set to begin in the last week of November. Following the approach used by Secretary Vince (Dizon) for the EDSA rehabilitation, we are on track to commence the C5 rehabilitation by the last week of November,” Lopez said in an interview during the inspection of the newly reopened Pasig Boulevard-C5 Flyover in Bagong Ilog, Pasig City Tuesday.

 

“The post-qualification phase of the bidding process is currently underway. Barring any unforeseen events, and based on the procurement timeline, we expect to issue the Notice of Award by November 16, followed by the Notice to Proceed a week later, provided there are no issues with the procurement process,” the DPWH chief added.

 

He explained that the key feature of this project is the expansion of the sidewalks, adopting the same template used for the EDSA rehabilitation where the sidewalks have been widened to accommodate not only pedestrians but also cyclists.

 

Lopez said the project spans from the Kalayaan Interchange all the way to Commonwealth Avenue (at Capitol Hills Drive), covering approximately 23 kilometers.

 

He reported that the funds to be used for the C5 rehab will come from the EDSA rehab funds.

 

“I am sharing this announcement because, much like the EDSA rehabilitation, we have managed to achieve significant cost savings. The original budget allocation was PHP17 billion, but under Secretary Vince’s leadership, this was reduced to PHP6 billion. The savings generated have been reallocated to the C5 rehabilitation. Consequently, both of these major arterial roads will be improved during the President’s term,” the Secretary added.

 

Meanwhile, Lopez said they are coordinating with the Metro Manila Development Authority (MMDA) and local government units regarding the traffic management plan while the project is ongoing.

 

“We are in close coordination with the MMDA and local government units. Construction will be carried out in phases,” he said.

 

He also reported that the project duration is 420 calendar days while working hours will be from 10 p.m. to 4 a.m.

 

“Completion is expected by the last week of January 2028. Careful planning is essential to ensure the project causes minimal disruption to the public. Just as we did in EDSA rehab,” the DPWH head said.

 

“Based on the scope of work, this involves rehabilitation, including base correction and an asphalt overlay. We will prioritize and begin work on any areas that are ready for construction. The DPWH now follows a ‘work on what is workable’ approach – if an area is ready for work, we proceed with it,” he added.

 

Meanwhile, the traffic flow on the Pasig Blvd-C5 Flyover in Bagong Ilog, Pasig City is now smoother and uninterrupted after the northbound lane was opened ahead of schedule at 12 noon Monday and the southbound lane at 12 midnight Tuesday.

 

According to Lopez, President Ferdinand Marcos Jr. ordered the immediate opening of the critical infrastructure to ease the travel of motorists and commuters returning home from the provinces and returning to work and school after Undas. (PNA Ferdinand G. Patinio)